Inadequate management of change – caused by:

  • Changes Inadequate management of change – caused by:
  • Changes made to engineering of mobile plant not included in process
  • Operational changes (routes, roads, numbers) not identified as a change and process not applied
  • Selected plant/kit/components do not meet site requirements
  • Steering or braking compromised by engineering changescompromised by engineering changes

 Credible Failure mode is addressed by:

  • BI-00D.01 There is a documented site Traffic Management Plan
  • BI-02D.01 Fit-for-purpose equipment selection and site use approval processes
  • BI-05P.01 Shift to shift communication
  • BI-05P.02 Site change management process apply to changes in equipment, road networks and traffic flows

VIEW RESOURCE